NEWS ANALYSIS | URN | Uganda may face an electricity shortage of nearly one gigawatt by 2030 if the government does not speed up investments in power generation and transmission, according to the Ministry of Energy and Mineral Development.
Uganda Radio Network has come across documents on projections that expose a growing challenge in the country’s electricity sector.
According to the documents and testimonies, the country has installed generation capacity of approximately 2,100 megawatts; some licensed power projects cannot supply electricity to the national grid because of inadequate transmission infrastructure, while operational challenges are limiting the availability of existing plants.
The Ministry of Energy has openly stated that electricity demand is growing rapidly, threatening to outstrip available generation capacity within the next four years.
Local and international experts say the government must embark on developing generation and grid infrastructure at a competitive cost to beat the challenge.
According to Eng. Julius Wamala , the Assistant Commissioner for Generation at the Ministry of Energy and Mineral Development, the country’s peak electricity demand reached 1,400 megawatts in June 2026, against firm generation capacity of approximately 1,650 megawatts.
He said demand was projected to grow by 15 percent annually, creating an increasingly difficult balance between electricity supply and consumption.
“When you look at the scenario, the forecast, when you look at 2027, once 2012 go into red, if we don’t do anything, we’re going to negatives of maybe 130 megawatts. When you look at 2028, we may go into deficits of 270 megawatts. When you go to 2029, we’re looking at almost 500 megawatts,” Wamala said.
“And then when you look at 2030, we’re looking at almost one gigawatt of a deficit. So I call upon everyone here; we need to work as a sector to see that we don’t go into such a state.
“The projections raise questions about whether planned investments in generation and transmission can be delivered quickly enough to prevent a supply crisis, at a time when existing generation and transmission infrastructure are already facing constraints.
It is evident that the country is not fully utilising generation capacity already developed or licensed.
Dr Frank Ssebowa, former Chief Executive Officer of the Electricity Regulatory Authority, has indicated that expanding generation without corresponding investments in transmission infrastructure could leave the country with electricity it cannot deliver to consumers.
“There is no point generating a lot of electricity unless you get into that word. Ugandans don’t want to hear about it. You know, deemed energy, have you ever heard of it? Many people don’t like it,” Ssebowa said.
He explained the problem with deemed energy, which arises when a power plant is ready to generate electricity but cannot supply it because the transmission infrastructure is unavailable.
” It means you have a plant sitting there; there is demand on the other side, but in between there is no transmission line,” he said.
Ssebowa said the country had approximately 5,300 kilometres of transmission lines by the end of 2025 but needed considerably more to meet its electricity ambitions.
He questioned the sequencing of generation and transmission investments, arguing that infrastructure bottlenecks must be addressed before additional generation projects are developed.
“Sometimes we have good ambitions. Someone was telling me that we have these very good ambitions, but we don’t look at the bottlenecks that are required to unlock these things,” he said.
The Ministry of Energy has indicated that approximately 325 megawatts of licensed renewable energy projects are yet to become operational.
Wamala said some of the existing generation capacity was not being efficiently evacuated because of inadequate network infrastructure.
“Even the capacity we do have on the ground is not efficiently evacuated. So we are looking at doing grid reinforcements and upgrades,” he said.
It has been noted that almost 80 megawatts of generation capacity in the Elgon region in eastern Uganda remains stranded.
The Ministry says the proposed 132-kilovolt Mbale-Bulambuli transmission line, being developed under the Independent Power Transmission model, is expected to help evacuate the electricity.
“That evacuation line, the Mbale-Bulambuli point line, the 132 kV line, has been promoted under the IPT model. I call upon our IPT partner; please, when we need your first tracking of that line,” he said.
“As government, as ministry, we are there to help you in all ways to see that that line comes on board in whatever circumstances so that we can tap into that capacity in that region.
“The Ministry is also considering reinforcing substations in the Rwenzori region, where network limitations are preventing the evacuation of approximately 14 megawatts.
Other proposed interventions include optimising small hydropower plants, some of which spill water that could potentially be used to generate electricity. The ministry estimates that these improvements could unlock approximately 30 megawatts.
Wamala said incentives for cogeneration companies could also encourage them to supply up to 100 megawatts of additional electricity to the national grid.
Transmission constraints are not the only problem affecting electricity supply. Operational challenges at Karuma Hydropower Plant, which has an installed capacity of 600 megawatts, could also affect the country’s ability to meet rising demand.
The government targets an increase in Karuma’s utilisation from approximately 21 percent to more than 50 percent by 2027.
According to Eng. Isaac Arinaitwe, Chief Projects Officer at the Uganda Electricity Generation Company Limited (UEGCL), the plant’s average generation had increased from approximately 65 megawatts in its first year of operation to nearly 300 megawatts in its third year.
He attributed the increase to rising electricity demand, which has seen Karuma absorb a substantial share of additional consumption.
However, he identified floating vegetation and debris from Lake Kyoga as a major challenge affecting the plant’s operations.
“Those have particularly challenged our plant operations. The floating islands coming out of Lake Kyoga are a challenge with excess debris. And in effect, that may be a problem that we need to address if we have to make those 600 megawatts available,” he said.
The problem resulted in significant generation losses last year.
“Last year, when we looked at our numbers, we lost about 4,800 hours of generation. Now, that is equivalent to losing a unit throughout the whole year. Or you could say, putting out the plant for a whole month,” Arinaitwe said.
He warned that operational difficulties could become more serious as electricity demand increases.
“Because when you need the 600, we may not have the 600,” he said.
UEGCL is considering capital investments to address the problem, alongside short-term removal of floating vegetation.

The company is also partnering with Ghana’s Volta River Authority to learn from its experience managing similar challenges at the Akosombo hydropower installation.
He explained that the problem needed to be addressed beyond the electricity generation subsector because it was connected to broader water resource management challenges.
The experience raises questions about the resilience of Uganda’s generation system, particularly its dependence on hydropower and the vulnerability of installations to environmental and operational disruptions.
Uganda’s National Energy Compact targets an increase in operational generation capacity from approximately 2,099 megawatts in 2025 to 2,500 megawatts by the end of 2030.It also seeks to bring approximately 5,800 megawatts of additional generation projects to financial close within the same period.
However, the two targets represent different stages of project development. Financial close means that a project has secured the financing required to proceed. It does not mean that the plant has been constructed or commissioned.
The additional 5,800 megawatts are expected to become operational after 2030, meaning they may not help address the supply deficit projected for the end of the decade.
The Ministry is considering several interventions, including refurbishment of the Nalubaale and Kiira hydropower stations and development of additional generation projects.
Wamala said the government was undertaking feasibility studies for the proposed 400-megawatt Kiba Hydroelectric Power Station.
He also identified thermal and gas-fired generation as possible additions to the electricity mix and said the government was working to accelerate regional electricity interconnections to strengthen energy security.
Uganda last month launched its National Energy Compact, setting ambitious targets to expand electricity access, strengthen clean cooking adoption and attract investments in the energy sector by 2030.
The compact was launched by the African Development Bank Group and the Government of Uganda, through the Ministry of Energy and Mineral Development.
The country plans to mobilise $17.7 billion in investments to achieve these objectives, including $9.4 billion in private-sector capital.
Attracting the investment will be important as the government seeks to involve private companies in developing transmission infrastructure.
However, the investment environment must be supported by infrastructure capable of accommodating additional electricity.
Wale Shonibare, Director of Energy Financial Solutions at the African Development Bank, said generation projects should be planned together with the needed transmission infrastructure and electricity demand to ensure they are viable.
“The new generation cannot deliver the intended benefits if the associated lines, substations, and customers are not ready,” Shonibare said.
He said the government needed to coordinate electricity generation with industrial investments and the infrastructure required to serve new consumers.”We have to align the demand and industrial investment with bringing on new generation capacity,” he said.
Shonibare said the discussion should identify immediate decisions needed to translate Uganda’s generation and transmission commitments into reliable electricity at competitive costs.
The Compact proposes competitive procurement, guarantees and blended financing to reduce investment risks. It also provides for private-sector participation in transmission infrastructure.
The government has introduced standardised power purchase agreements and implementation agreements and revised renewable energy feed-in tariffs in an effort to improve the investment environment.
The National Energy Compact provides a framework for addressing the electricity sector’s challenges. It targets expansion of the distribution network, reduction of distribution losses from 16 percent in 2025 to below 12 percent by 2030, and increased access to electricity and modern cooking solutions.
The country‘s compact targets 85% electricity access and 50% access to clean cooking by 2030. It also aims to achieve approximately 2,500 MW of operational power generation capacity, with an additional 5,800 MW reaching financial close for commissioning after 2030.
Other targets include developing 2,712 mini-grids and increasing regional electricity exports to between 500 MW and 650 MW.
It also seeks to mobilise private investment and strengthen regional electricity trade.
The Compact provides for a Delivery and Monitoring Unit within the Ministry of Energy and Mineral Development, which is expected to publish quarterly progress reports, annual delivery reviews and a digital results dashboard.
Dr. Frank Ssebowa said the sector needed to move beyond ambitious targets and identify investments and decisions that could be implemented immediately.”I don’t know how many, but I agree some steps must be done in the next six months,” he said.
“I say this because 2030 is hardly two or three years away, and there are things that must be done if the government compact, if our Ugandan energy compact, is going to be met.”
*****